We performed a significant refurbishment for a South Yorkshire Public Mortuary.
+100 mortuary storage capacity including, fridge & freezers cabinets, cold room and mortuary equipment.
Here we planned and set up temporary fridges prior to a phase 1 removal of existing, to ensure the customer had sufficient capacity for their very busy environment. Once phase 1 was successfully operational we handed over this area to move on to phase 2 and then onto phase 3.
We planned and saved our customer tens of thousands of pounds by setting up the temporary fridge’s to be later repositioned to their final phase 3 locations.
We worked under ESH Construction for this major multi million pound refurbishment of the whole the whole facility.