Working closely with the clients builder we supplied a detailed CAD plan of this project, the room was awkward in space for capacity desired as well that the right hand wall kicked in, we had to ensure there was suitable space for the loading area trolley to align with the right hand door, our space saving cabinet enabled this without compromising the loss of the bariatric bay that was required.
The program of works was kept to an absolute minimum and needed to be as the customer needed their existing cold room removing and the works completed ASAP to reopen the facility. Our engineers traveled down the evening before to start bright and early and worked late into the evening, returning the next day to be finished by lunch time!
Post these images the builder has installed as suspended ceiling, fit trim to finish the fridge to wall and plumbed our double embalming sink and wash hand basin. (further images to be added)
Supplied with bariatric trolley (wider top with double ram 65stone capacity) stainless steel with tray tilt feature to use as a embalming trolley over sink as well as stacking the fridge. Complete with weighing device.
We will always work hand in hand with builders supplying plans and communicate with them all the way through to make any task run smoothly.
Post the completion we have been advised that the highly experienced funeral home building contractors gave us high praise over previous poor mortuary suppliers.